In 2023, Cognition Land and Water was appointed by Nelson Land and PSP Consulting to undertake remediation and enabling works at the former Newbury Gas Works site. Located within the Sterling Industrial Estate, the site had a long legacy of industrial use, resulting in significant contamination within a densely developed area of Newbury.
The project demanded stringent environmental monitoring to minimise impact on the surrounding community. Its proximity to an active railway line required all works to be carried out under a strict asset protection agreement with Network Rail. Additionally, demolition was needed for a redundant building adjoining an operational office and workshop.
Remediation Scope
Cognition’s primary objective was to remediate the site to reduce environmental and human health risks, enabling its transformation into a residential development. The key remediation activities included:
To remove NAPL effectively, Cognition deployed its proprietary FabEx fabric extraction system, which allowed targeted removal without the need to extract and treat large volumes of groundwater.
In total, 17,000m³ of contaminated soil was successfully remediated to meet residential criteria. The FabEx system reduced NAPL to less than 5mm thickness at the groundwater interface. A protective PRB wall was installed around the site to prevent offsite migration of contaminants.
Community Engagement
All works were completed with minimal disruption to local residents. Cognition maintained an open and proactive engagement process, issuing regular newsletters and hosting site visits for both the Local Authority and the Environment Agency. This transparent approach was commended by regulators, particularly given the site's visibility from surrounding properties.
Concrete Frame Construction
Following the successful remediation phase, Cognition was invited to construct the reinforced concrete-framed structure for the new residential development. This phase included:
Cognition’s prior knowledge of the site enabled design optimisations that delivered both cost and programme benefits. Notable improvements included:
These design changes resulted in significant savings and improved efficiency for the client.
Learn More
To explore how Cognition expertly delivered this complex and multi-phase project, visit our case study:https://www.cognitionlandandwater.com/case-studies/Newbury-Gas-Works/