Cognition’s Progress at Bow Common Phase 2…

4 March 2026

Cognition continues to make excellent progress on our enabling works for Phase 2 of the Bow Green development on behalf of our client, St James (Berkeley Group).

Since works began, we have completed the:

  • Moving of 3no. Stockpiles out of Phase 2 area
  • Construction of a haul road
  • Augering for pile positions
  • Turnover in lift shaft, core and deep drainage areas
  • Removal of viaduct wall
  • Reduced dig for pile mat
  • Removal of Knapp Road Wall

Now that these elements are complete, we are currently carrying out the following works:

  • Fill of pile mat to finish level reusing onsite material
  • Crushing of concrete stockpile for reuse on site
  • Off-site removal of non-hazardous material

Cognition is deeply committed to the quality, safety and sustainability of our project delivery. We look forward to our continued collaboration with the rest of the team at Bow Common - Phase 2 as we help deliver this transformative project!